Працював в 9 компаніях   16 років 6 місяців

Енергетика та Енергоносії, Промисловість та Виробництво, Будівництво, Інше

Planning Engineer

EMERGY Ukraine, Zophia Wind Farm Project

Енергетика та Енергоносії

1 рік 3 місяці

10.2020 - 01.2022

Development detail schedules for various scenario of Wind Farm Construction including all discipline (civil (roads, foundations), electrical (substation OHL, 35 kV grid), TSA (WTG erection, commissioning, take over)). Progress measurement system and reports preparation by individual construction discipline.

Planning Manager

Power Construction Corporation of China, LTD

Енергетика та Енергоносії

1 рік 2 місяці

07.2019 - 09.2020

Project - 250 MW Syvash wind power project, one of the largest onshore wind farms in Ukraine 63 WTG's. EPC Contractor (FIDIC Contract). Master Plan (level 5) development for all civil works (roads, foundations construction), substation construction and installation of WTG’s including commissioning activity. Daily progress, manpower recourses avalability monitoring on construction site. Weekly, Monthly Progress reports preparation, progress percent complete calculation. Critical path of schedule analysis.Corrective action preparation in case of progress delay.

Planning engineer

DANIELI & C. Officine Meccaniche S.p.A.

Промисловість та Виробництво

5 місяців

01.2019 - 06.2019

Project - supervision of new equipment installation for Threading Line, Quality Control Line and Heat Treatment Line of Pipes at Vyksa Pipe Works Shop.Progress monitoring according baseline schedule during the erection and commissioning process. Daily progress, manpower recourses avalability monitoring on construction site. Daily, Weekly Progress reports preparation, progress percent complete calculation. Corrective action preparation togather with Client in case of progress delay.

Senior Project Control engineer

Arcelor Mittal Krivoy Rog

Промисловість та Виробництво

11 місяців

03.2017 - 02.2018

Project – site preparation and LFCC2,3 construction.Brownfield construction, engineering networks, operations facilities relocation. New LFCC2 and LFCC3 construction.Development and approval of WBS and schedules with contractors, Master Schedule development. Progress monitoring according baseline schedule. Daily progress, manpower recourses avalability monitoring on construction site, holding daily meetings with the contractors. Daily, Weekly Progress reports preparation, progress percent complete calculation. Corrective action preparation in case of progress delay.

Planner

LUKOIL Overseas Service B.V. (Dubai Branch)

Будівництво

3 роки 1 місяць

11.2012 - 12.2015


West Qurna 2 Project, Gas Treatment Plant EPC.

Duties consist of development and update of Project Master Schedules. Interact with master planning department for schedule update matters. Detect schedule critical paths. Interact with team on schedule critical paths. Update of Project Weekly / Monthly Reports. Report on schedule deviations from baselines. Follow up of work performed by contractor as per approved procedures / contract. Review / record of instructions / changes (schedule impacts) associated to work performed by contractor. Review of contractor's status reports. Monitoring of progress in line with the project calendar. Review of contractor Planning Packages / baseline plans. Ensure contractor is not deviating from approved baseline plans.

Site Planner

Total E&P Russia Company, Russia Kharyaga

Будівництво

11 місяців

12.2011 - 11.2012

Kharyaga Phase III Development Project

Duties consisted preparation of Primavera construction schedules for pipelines, OHL and surface facilities, control of construction progress at daily basis and Daily, Weekly Progress Reports preparation.

Senior Planning Engineer

Regal Petroleum plc, drilling site (Ukraine)

Інше

3 роки 2 місяці

06.2008 - 08.2011


Mekhedivske-Sviridivske & Golotovschinske Gas field development.

Responsible for the preparation of Gas Field Development Plan, progress control on weekly basis, critical path analysis etc.

Senior Business Support Planner

Sakhalin Energy, Yuzhno-Sakhalinsk

Будівництво

1 рік 7 місяців

11.2006 - 06.2008


Responsible for Planning and Progress Reporting of assets readiness to operate and commission Sakhalin 2 Oil & Gas Project.

My primary responsibility is the preparation of MS Project or Primavera Schedules analysing progress and critical path, which shows in our Monthly Management Reports.

Senior Planning Engineer

Nippon Steel Corporation, Moscow and Yuzhno-Sakhalinsk

Будівництво

3 роки 6 місяців

05.2003 - 11.2006


Responsible for all Planning and Progress Reporting for the Sakhalin 1 Phase 1 Development Project, Pipeline.

Duties include directly supervising an "Offshore" Planner based in Tokyo, and an "Onshore" Planner based at site.

My primary responsibility is the preparation of Primavera Schedules which "roll up" progress into our Weekly and Monthly Management Reports.

The Project consists of the construction of 228 km of 24" On/Offshore pipeline with associated Valve Stations and Pig Launcher/Receiver facilities on Sakhalin Island, across Tatar Strait, and on the Russian Mainland, plus a 12 km flowline section of 24" and 36" lines.

Ключова інформація

More then 20 years experience in Project Control, various industries, mostly in Oil & Gas and Renewable Energy.

Навчався в 1 закладі

МИСиС

Металлургия цветных металлов

Россия, 1991

Володіє мовами

Англійська

вище середнього

Може проходити співбесіду на цій мові

Може проходити співбесіду на цій мові

Курси, тренінги, сертифікати

- Primavera P6 Professional Fundamentals rel 8.2 (P6 Course 706) CMCS, Primavera P6 Professional.

Другие страны, 2013

- Primavera P6 Professional Advanced rel 8.2 (P6 Course 705) CMCS, Primavera P6 Professional.

Другие страны, 2013

- Managing Risk in Primavera Risk Analysis Rel 8.6 Ed 1 PRV Oracle University, Risk Analysis.

Другие страны, 2013

- Managing Risk in Primavera Risk Analysis Rel 8.6 CMCS, Risk Analysis.

Другие страны, 2013

Victor

Planning, Scheduling, Project Control

Інші країни

Готовий переїхати: Київ

57 років

Активно шукає роботу

повна зайнятість, проектна робота

Характер роботи: віддалена робота, гібридна, в офісі/на місці

Оновлено 1 день тому