Працював в 16 компаніях   24 роки 9 місяців

Будівництво, Охорона та Безпека, Туризм / Подорожі / Пасажирські перевезення, Нерухомість та Девелопмент, Консалтинг / Аудит

Technical Director

Enki Construction LLC

Будівництво

2 роки 4 місяці

05.2022 - до теперішнього часу

Development of conceptual projects for the reconstruction of destroyed public buildings (Lyceum No. 3 in Irpin, kindergarten in Makariv, Youth Centre and Stadium in Chernihiv).

Organisation and launch of works under the contract with UNHCR (replacement of windows in the affected buildings and houses for IDPs)

Volunteer of the territorial defence battalion

Territorial defence of Kyiv

Охорона та Безпека

3 місяці

02.2022 - 05.2022

Duty at the roadblock

Project and construction manager

Delta Proektconsult Ukraine

Будівництво

10 місяців

04.2021 - 02.2022

Recovery after a fire with a complete technical modernization of the ski workshop of the Fischer factory (Austria) 21,000 m2.

Communication and coordination between Austrian and Ukrainian project participants. Control over the work of the general and subcontractors.

Preparation and commissioning in February 2022

Technical Director/Project Manager

Dragon Capital

Будівництво

3 роки

04.2018 - 04.2021

Customer representative office: Chief engineer

KPBK LLC, Kyiv

Будівництво

1 рік

04.2017 - 04.2018

Construction work organization and follow up for business center class "A" site (50 000m2).

Customer representative office: Chief engineer

Kaspian Service, LLC

Будівництво

6 місяців

10.2016 - 04.2017

Follow up for project documents, design and construction of residential and industrial facilities. Processing the contracts with contractors and suppliers. Preparing construction plans and schedules. Construction works quality managenent. Development of optimal technical solutions.

Residential complexes (comfort class 3.5 hectares).

Complex fuel (petrol-gas) stations/

Chief Executive Officer

Ermastar LLC, Prague

Туризм / Подорожі / Пасажирські перевезення

10 місяців

12.2015 - 10.2016

Organization of outbound tourist services with guide support for individual and groups of tourists. Design of exclusive tourist programmes.

Czech Pepublic, Germany, Austria, Slovakia, Hungary

Chief engineer

Kulan Kypshak LLC

Будівництво

2 місяці

09.2015 - 11.2015

Start-project for autonomic ukrainian unit of kazakh construction company. Recruiting, organizational structure and business process design, construction works performing and follow up, procurement management for materials, tools and equipment. Other construction services for ASTANA EXPO-2017 construction.

Chief Executive Officer

Ermastar LLC, Prague

Туризм / Подорожі / Пасажирські перевезення

1 рік 4 місяці

05.2014 - 09.2015

Organization of outbound tourist services with guide support for individual and groups of tourists. Design of exclusive tourist programmes.

Czech Pepublic, Germany, Austria, Slovakia, Hungary

Customer representative office: Chief engineer

“Megapoliszhytlobud” LLC (member of “DF group”)

Нерухомість та Девелопмент

8 місяців

09.2013 - 05.2014

Development of design and construction schedules; project budgeting (cost sheet reporting);

Control of construction process ( scheduling, quality)

Design and expertise of optimal technical solutions, selection of contractors, equipment and materials.

Support of projects' technical supervision

Adjustment of the leaseholders' technical requests

Objects: 3*hotel (historical building reconstruction),

"Inter broadcasting" TV center building construction

Multifunctional complex "Respublika" (290 thou m sq.).

Customer representative office: Chief engineer

Millenium Tour LLC (member of “DF Group”)

Нерухомість та Девелопмент

1 рік

09.2012 - 09.2013

Development of design and construction schedules; project budgeting (cost sheet reporting);

Control of construction process ( scheduling, quality)

Design and expertise of optimal technical solutions, selection of contractors, equipment and materials.

Support of projects' technical supervision.

Objects: 5* and 4* hotels, Oreanda, Crimea

Chief engineer of the construction project

Company for the construction projects management “Hertz” (DF group contractor)

Будівництво

3 місяці

05.2012 - 08.2012

Co-ordination and control for project design papers,

Expertise and confirmation of technical solution within hotel's construction project,

Searching and engagement of European construction design bureaus,

Co-ordination and control of project

Customer representative office: Head of General Contractor’s Group, Director for supervision (at th

“Kanterinvest” LLC, “Komkonsultant” LLC

Будівництво

2 роки 8 місяців

04.2009 - 12.2011

Co-ordination of the project design development (selection of design contractors, contraction, control for design quality );

Providing of tender procedures for construction and specialized construction activities;

Development of design and construction schedules; project budgeting;

Design and expertise of optimal technical solutions, selection of equipment and materials.

Management of the company technical supervision.

Multifunctional complex of B+ class in Zaporozhye (2 hectares), Reconstruction of the resort complex "Zolotoy Plyazh", Livadiya, Crimea (6 hectares),

Construction of the "Victoria" 5 * hotel, Livadia, Crimea (5 hectares).

Chief engineer

JSC «Terra Development»

Нерухомість та Девелопмент

3 місяці

07.2008 - 10.2008

Creation of the technical department of building owner; management and control: technical supervision, monitoring of the working drawing processes, pricing, choice of contractors, preparation and tender providing for "Altagrad" residential complex (Boryspil, site area is 2.00 hectares, useful area 70 ooo sq.m)

Construction consultant

JSC «Savant Ukraine» (GB)

Консалтинг / Аудит

3 роки

06.2005 - 06.2008

Construction management, management of the engineering supervision group, monitoring of the working drawing processes for "Seven Hills" residential complex (Kyiv, site area is 3,96 hectares, useful area 200 ooo sq.m, June 2007 - June 2008)

Engineering supervision and management of engineering underground pipelines and services for construction site of "Bunge" solvent-extraction plant (Illichivsk, Odesa oblast, site area is 5,2 hectares, August 2006 - June 2007)

Engineering supervision and management of engineering services for "Procrter&Gamble" plant's construction site (Boryspil, Kyiv oblast, site area is 2 hectares, June 2005 - July 2006)

Chief engineer

„Construction Company “Stroymontazh” Ltd.

Будівництво

6 років 2 місяці

04.1999 - 06.2005

Construction management (monitoring of the working drawing, building, fit-out, engineering services processes) for JSC "Ukrtelecom" building and premises reconstruction ( April 1999 - December 2000).

Construction management, management of the engineering supervision group, monitoring of the working drawing processes for "Dnistovska hydroelectric pumped storage power plant" servicing buildings and premises (Novodnistrovs'k, January 2001 - June 2005)

Навчався в 1 закладі

Kyiv National University of Construction and Architecture (during studying – Kyiv Civil Engineering Institute)

Industrial and civil construction faculty

Kyiv, Ukraine, 1992

Володіє мовами

Англійська

середній

Чеська

середній

Російська

рідна

Українська

вільно

Курси, тренінги, сертифікати

Ministry of regional development and construction of Ukraine

Kyiv, Ukraine, 2010

Specialist (engineer) for engineering supervision of 2nd category , IT № 003232

Ukrainian National Academy of environmental and recreation construction

Simferopol, Ukraine, 2009

Construction of building in seismic areas and difficult geotechnical conditions

СО № 10207

Додаткова інформація

Driving License

A,B, C, D, E category. Private motor-car is accessible.

Computer Skills

experienced user (MS Office - Word, Excel, Internet, Outlook, Project, AutoCAD, Photoshop CS)

Igor

Project Manager, Head of Construction

Київ

2 000 $

56 років

повна зайнятість

Оновлено 4 місяці тому